Case Study ® ABB 2024
Centrin Data Systems
Data Centers
Power Distribution
Fast deployment of ABB digital solution ensures power availability to a Centrin Data Systems data center
Digital medium-voltage solution
China
Challenge
Power supply to computer room
Solution
216 panels UniGear ZS1 medium-voltage switchgear with Relion® protection relays. The project included an advanced automatic switching solution with Relion 615 series protection relays for IEC 61850 standard-based digital communication and GOOSE messaging.
Outcome
A digital solution for a large-scale advanced data center in East China with over 80% faster commissioning and reduced on-site wiring and  40% reduction in project delivery time.
80% 
Faster commissioning
Reduced on-site wiring
40% 
Reduced project
delivery time