ABB Stonehouse facility in the UK aimed to improve energy productivity and reduce operational costs but lacked accurate data for making targeted changes.
ABB deployed its digital technology, ABB Ability™ Building Analyzer, along with multiple energy monitoring devices including 29 electrical sub-meters (ABB M4M Power Meters), gas meters, water meters (ABB Aqua Master 4), utility gas meters, and utility electric meters. These devices were integrated into the Building Analyzer system, providing comprehensive tracking of energy consumption and enabling personnel to monitor and analyze electricity and utility consumption in real time.
The implementation of ABB Ability™ Building Analyzer at the Stonehouse facility resulted in substantial energy savings, with a 20% improvement in electricity consumption alone, and the identification of opportunities for improvement leading to significant cost savings and sustainability benefits.